National Grid

Construction Update NOTICE:

  • October 17 thru October 24 we will be doing the Horizontal Directional Drilling on Ocean St and Hawes St. In Hyannis
  • October 24 thru October 31 we will be doing the Horizontal Directional Drilling on Jefferson Ave in Nantucket.
  • The Submarine Cable Installation will begin in Late November - Early December.

The map included in this section summarizes what has been accomplished to date and where construction crews are expected to be working in the coming months. Please keep in mind that weather conditions may impact construction schedules.

Completed areas: manhole and conduit installation is complete. Cable installation and final street restoration work will occur in the fall of 2005. These activities will not require any excavation in the public way.


Barnstable Cable Route

Nantucket Cable Route


If you would like additional information or have questions, please contact us or call at 508-325-8216.