Generators desiring to connect to New England Power Company's transmission system shall follow the procedures identified below and in accordance with Schedule 22 and Schedule 23 of the ISO New England Inc. Transmission, Markets and Services Tariff:
Generator Interconnections of 20MW or Lessreference Schedule 23
- Eligible customers will first complete a Small Generator Interconnection Application.
- The completed Interconnection Request may be sent or faxed to:
ISO New England Inc.
Attn: System Planning Department
Manager, Transmission Planning
One Sullivan Road
Holyoke, MA 01040
Fax: 413-535-4127
- Upon receiving the completed Interconnection Request the ISO will determine which Transmission Owner will provide the studies.
Generator Interconnections of Greater than 20MWreference Schedule 22
- Eligible customers will first complete a Large Generator Interconnection Application.
- The completed Large Generator Interconnection Application may be faxed to:
ISO New England Inc.
Attn: System Planning Department
Manager, Transmission Planning
One Sullivan Road
Holyoke, MA 01040
Fax: 413-535-4127
- Upon receiving the completed Interconnection Request the ISO will determine which Transmission Owner will provide the studies.
Questions may be directed to ISO-NE at custserv@iso-ne.com.