News and Updates
2024
In October 2024, the community can expect the following activities:
- Excavation activities
- Backfill activities
In September 2024, the community can expect the following activities:
- Continued installation of upgraded infrastructure.
- Crane activities.
- Some 24-hour crew presence for monitoring of the new infrastructure.
- Tie-in activities.
- Welding activities.
In August 2024, the community can expect the following activities:
- Continued installation of upgraded infrastructure.
- Crane activities.
This month you can expect the following activities:
- Continued excavations within the Long Beach Gate Station.
- Installation of upgraded infrastructure.
- Welding activities.
This month you can expect the following activities:
- Continued excavations within the Long Beach Gate Station.
- Crane activities to unload infrastructure.
- Prefabrication activities.
*Starting the week of 06/03/2024, crews will be working Saturdays from 7AM to 5PM to increase the project's productivity.
This month you can expect the following activities:
- Excavations within the Long Beach Gate Station.
- Dewatering of retired main.
- Prefabrication activities.
This month you can expect the following activities:
- Mobilization of materials into the yard.
- Prefabrication activities.
- Excavations within the Long Beach Gate Station.
This month you can expect to see crews mobilizing materials and preparing the yard for construction to start in April 2024.