Project Schedule

Construction Activities:

  • Construction of Marshalling Yards: Late Spring 2024
  • Construction Start: Fall 2024
  • Anticipated Construction End: Winter 2026

 

Upcoming Activities:

2026

  • Work will be completed on the North Watertown to Indian River line in March of 2026.
  • Restoration will continue until the end of 2026.
  • Questions about the restoration efforts can be emailed to UpstateUpgradeCNY@nationalgrid.com.
  • Final Conductor Pulling at the structure locations in Pamelia near Perch River Wildlife Management Area.
  • Substation to support energization and restoration until 80% vegetation is reached across the entire right of way.
  • Conductor Pulling (Stringing Wire) at structure locations in Pamelia near Perch River Wildlife Management Area.
  • Conductor Pulling (Stringing Wire) at structure locations in Pamelia near Perch River Wildlife Management Area.
  • Conductor Pulling (Stringing Wire) at structure locations in Pamelia near Perch River Wildlife Management Area.
  • No significant work scheduled (weather impact).
  • Installing miscellaneous signage on structures.
  • Drilling foundations complete.
  • No significant work scheduled.

2025

  • Foundation drilling and pouring in Brownville near Star School House Road continues.
  • Foundation drilling and pouring in Brownville near Star School House Road
  • Site restoration efforts across the towns of Brownville, Pamelia, and Le Ray
  • Structure drilling in Brownville near state route 12
  • Temporary transmission line energization across the towns of Brownville, Pamelia, and Le Ray
  • Site restoration efforts across the towns of Brownville, Pamelia, and Le Ray
  • No significant work scheduled
  • No significant work scheduled
  • Equipment Installation at the new North Watertown Substation in Brownville near Vaadi Road and NYS Route 12
  • Equipment Installation at the new North Watertown Substation in Brownville near Vaadi Road and NYS Route 12
  • Equipment Installation at the new North Watertown Substation in Brownville near Vaadi Road and NYS Route 12
  • Foundation Pouring in Le Ray near US Route 11 at the Indian River Substation
  • Structure Drilling in Le Ray near US Route 11 at the Indian River Substation
  • Foundation Pouring in Le Ray near US Route 11 at the Indian River Substation
  • Structure Drilling in Le Ray near US Route 11 at the Indian River Substation
  • Foundation Pouring in Le Ray near US Route 11 at the Indian River Substation
  • Structure Drilling in Le Ray near US Route 11 at the Indian River Substation
  • Foundation Pouring near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Structure Drilling near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Foundation Pouring near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Structure Drilling near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Foundation Pouring near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Structure Drilling near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Foundation Pouring near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Structure Drilling near new North Watertown Substation at Structure Locations in Brownville off NYS Route 12
  • Temporary Wire (Conductor) to Structure Erection at Structure Locations in Pamelia near Perch Lake Road, NYS Route 12, and Bonney Road
  • Site Restoration Brownville at Structure Locations near NYS Route 12, Star School House Road and Bonney Road, and in Pamelia at Structure Locations near Parish Road
  • Matting Configuration in Le Ray at and near Indian River Substation
  • Foundation Pouring at Structure Locations near Indian River Substation in Le Ray near US Route 11 
  • Structure Drilling at Structure Locations near Indian River Substation in Le Ray near US Route 11 
  • Foundation Pouring at Structure Locations in Brownville near NYS Route 12
  • Foundation Pouring at Structure Locations in Brownville near NYS Route 12 
  • Structure Drilling at Structure Locations in Brownville near NYS Route 12 
  • Above-ground Foundation Construction at new North Watertown Substation Site in Brownville near Vaadi Road and NYS Route 12
  • Temporary Wire (Conductor) to Structure Erection at Structure Locations in Brownville near Star School House Road, NYS Route 12, and Bonney Road
  • Foundation Pouring at Structure Locations in Brownville near NYS Route 12
  • Structure Drilling at Structure Locations in Brownville near NYS Route 12 and Star School House Road
  • Site Restoration at Locations in Brownville near Bonney Road and Parish Road, and in Pamelia near Parish Road and Knowlesville Road
  • Matting Reconfiguration at Project Site Locations in Brownville near Bonney Road and Parish Road, and in Pamelia near Parish Road and Knowlesville Road
  • Fence Installation in Pamelia near Parish Road
  • Temporary Transmission Wire (Conductor) to Structure Attachment and Stringing (Pulling) Execution at Structure Locations in Brownville near NYS Route 12 and Star School House Road
  • Site Restoration at Locations in Le Ray near Jenkins Road (County Route 16)
  • Matting Reconfiguration at Project Site Locations in Brownville near Bonney Road and Parish Road, and in Pamelia near Parish Road, Knowlesville Road, and Perch Lake Road
  • Site Restoration at Locations in Le Ray near Jenkins Road (County Route 16)
  • Wire (Conductor) Preparation at Structure Locations in Pamelia near Perch Lake Road and County Route 16
  • Matting Reconfiguration at Project Site Locations in Pamelia near Perch Lake Road and Knowlesville Road
  • Foundation Pouring at Structure Location in Brownville near NYS Route 12
  • Site Restoration at Locations in Le Ray near Jenkins Road (County Route 16)
  • Wire (Conductor) to Structure Attachment and Stringing (Pulling) Execution at Structure Locations in Pamelia near Perch Lake Road and County Route 16
  • Foundation Pouring at Structure Location in Brownville near NYS Route 12
  • Structure Drilling Preparation at Structure Location in Brownville near NYS Route 12
  • Foundation Pouring at Structure Location in Brownville near NYS Route 12
  • Wire (Conductor) Preparation at Structure Locations in Pamelia near Perch Lake Road and County Route 16
  • Matting Installation in Brownville near NYS Route 12
  • Matting Reconfiguration at Project Site Locations in Pamelia near NYS Route 37 and in Le Ray near Jenkins Road - County Route 16
  • Wiring Stringing (Pulling) Execution at Structure Locations in Pamelia near Perch Lake Road and Knowlesville Road
  • Structure Drilling Preparation at Structure Location in Brownville near Star School House Rd and NYS Route 12
  • Matting Reconfiguration at Project Site Locations in Pamelia near Knowlesville Road, NYS Route 37, and Perch Lake Road
  • Site Restoration at Structure Locations in Pamelia near Knowlesville Road and NYS Route 37
  • Rock Cleanup at Project Site Locations in Pamelia near Knowlesville Road and NYS Route 37
  • Wiring Stringing (Pulling) Execution at Structure Locations in Pamelia near Perch Lake Road and Knowlesville Road
  • Wire (Conductor) Preparation at Structure Locations in Pamelia near Perch Lake Road and Knowlesville Road
  • Matting Reconfiguration at Project Site Locations in Pamelia near NYS Route 37
  • Site Restoration at Project Site Locations in Pamelia near NYS Route 37 and Knowlesville Road
  • Rock Cleanup at Project Site Locations in Pamelia near NYS Route 37 and Knowlesville Road
  • Structure Placement and Support for Structures at Locations in Brownville near Bonney Road and Parish Road, in Pamelia near Parish Road, Knowlessville Road, and Perch Lake Road and County Route 16
  • Structure Drilling at Structure Locations in Brownville near Star School House Road
  • Installation of Turtle Fencing and Barriers in Brownville near NYS Route 12
  • Matting at Project Site Locations in Brownville near NYS Route 12
  • Construction of Access Roads in Brownville near NYS Route 12
  • Site Restoration at Project Site Locations in Pamelia near NYS Route 37 and in Le Ray near Jenkins Rod - County Route 16
  • Matting Reconfiguration at Project Site Locations in Pamelia near NYS Route 37 and in Le Ray near Jenkins Rod - County Route 16
  • Structure Placement and Support for Structures at Locations in Brownville near Bonney Road and Parish Road, in Pamelia near Parish Road, Knowlesville Road, and Perch Lake Road and County Route 16
  • Structure Drilling and Foundation Pouring at Structure Location in Brownville near Bonney Road
  • Structure Drilling at Structure Location in Brownville near Star School House Road
  • Construction of Access Roads in Brownville near NYS Route 12
  • Matting at Project Site Locations in Brownville near NYS Route 12
  • Installation of Turtle Fencing and Barriers in Brownville near NYS Route 12
  • Matting Reconfiguration at Project Site Locations in Pamelia near NYS Route 37 and in Le Ray near Jenkins Road - County Route 16
  • Structure Placement and Support for Structures at Locations in Brownville near Bonney Road and Parish Road, in Pamelia near Parish Road, Knowlesville Road, and Perch Lake Road and County Route 16
  • Structure Drilling and Foundation Pouring at Structure Location in Pamelia near Perch Lake Rd and County Route 16
  • Structure Drilling at Locations in Pamelia near Knowlesville Road
  • Installation of Turtle Fencing and Barriers in Pamelia near NYS Route 37
  • Site Restoration in Le Ray near Jenkins Rod - County Route 16
  • Matting at Project Site Locations in Brownville near NYS Route 12
  • Gravel Access Work in Brownville near NYS Route 12
  • Drilling at Structure Locations in Pamelia near Perch Lake Road and County Route 16
  • Drilling at Structure Locations in Pamelia near Perch Lake Road 
  • Foundation Pouring at Structure Location in Pamelia near Perch Lake Rd and County Route 16
  • Matting Reconfiguration at Project Site Locations in Brownville near Star School House Road and NYS Route 12
  • Installation of Turtle Fencing and Barriers in Brownville near Star School House Road
  • Site Restoration of Access Roads in Pamelia near County Route 16
  • Drilling at Structure Locations in Pamelia near Perch Lake Rd and County Route 16
  • Matting Reconfiguration at Project Site Locations in Pamelia near NYS Route 37 and Brownville near Star School House Road and NYS Route 12
  • Installation of Turtle Fencing and Barriers in Brownville near Star School House Road
  • Site Restoration of Access Roads in Brownville near Star School House Road and NYS Route 12
  • Removal of Stone at Project Site Locations in Le Ray near US Route 11 and Jenkins Rd - County Route 16
  • Access Matting Work at Project Site Locations in Brownville near Star School House Road
  • Fence Installation at Project Site Location in Le Ray near Jenkins Rd - County Route 16
  • Drilling and Concrete Pouring at Structure Location in Brownville near Bonney Road 
  • Drilling at Structure Location in Brownville near Star School House Road
  • Drilling at Structure Locations in Pamelia by Knowlesville Road near Parish Rd, County Route 16 and Perch Lake Road
  • Structure Drilling at Structure Locations in Brownville near Parish Road and Bonney Road 
  • Continued Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near NYS Route 37 to NYS Route 37 to Knowlesville Road
  • Ongoing site restoration near US Route 11 to Jenkins Rd - County Route 16 in Le Ray
  • Structure Drilling at Structure Locations in Pamelia and Brownville near Parish Road 
  • Continued Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near NYS Route 37 to NYS Route 37 to Knowlesville Road
  • Structure Drilling and Concrete Filling at Structure Locations in Pamelia near Parish Road 
  • Continued Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near NYS Route 37 to NYS Route 37 to Knowlesville Road 
  • Matting Reconfiguration in Le Ray near US Route 11, Jenkins Road - County Route 16 and NYS Route 37 to locations in Pamelia near Perch Lake Road to County Route 16 to Knowlesville Road
  • Installation of Turtle Fencing in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37
  • Site Restoration in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37
  • Electrical and Civil Construction in Le Ray near US Route 11 at the Indian River Substation
  • Matting Reconfiguration in Pamelia near Perch Lake Road to County Route 16 to Knowlesville Road 
  • ⁠Installation of Turtle Fencing and Barriers in Le Ray near US Route 11
  • ⁠Site Restoration in Le Ray near US Route 11
  • ⁠Electrical and Civil Construction in Le Ray near US Route 11 at the Indian River Substation

  • ⁠Installation of Turtle Fencing and Barriers in Pamelia near Knowlesville Road and NYS Route 37
  • Continued Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 to NYS Route 37 
  • Matting Reconfiguration and Access Road Installation starting in Le Ray near US Route 11 to Parish Road to Bonney Road in Brownville 
  • Site Restoration in Le Ray near US Route 11
  • Electrical and Civil Construction in Le Ray near US Route 11 at the Indian River Substation
  • Structure Setting at Locations in Pamelia near NYS Route 37, Knowlesville Road, and Perch Lake Road
  • Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
  • No Structure Installation Work Scheduled
  • Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 and US Route 11
  • Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
  • Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 and US Route 11
  • Foundation Pouring at Structure Locations in Le Ray near NYS Route 37, and Jenkins Road - County Route 16 and US Route 11
  • Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
  • Foundation Pouring at Structure Location in Pamelia near Kowlesville Road 
  • Wire Stringing (Pulling) Preparation at Structure Locations in Le Ray near NYS Route 37, and Jenkins Road - County Route 16 and US Route 11
  • Installation of Turtle Fencing in Pamelia near Knowlesville Road and NYS Route 37
  • Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
 
  • Structure Drilling and Concrete Filling at Structure Locations in Pamelia near NYS Route 37 and Knowlesville Road 
  • Structure Drilling and Concrete Filling at Structure Locations in Pamelia near Knowlesville Road 
  • Structure Drilling and Rock Extraction at Structure Location in Pamelia near Kowlesville Road
  • Matting Installation and Construction of Gravel Access Roads in Brownville near Star School House Road and Bonney Road 
  • Wire Stringing (Pulling) Preparation and Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 and US Route 11 

 
  • Concrete Pouring at Structure Location in Pamelia near NYS Route 37 
  • Structure Drilling and Concrete Filling at Structure Location in Pamelia near NYS Route 37 
  • Structure Drilling and Concrete Filling at Structure Location in Pamelia near NYS Route 37 and Knowlesville Road 
  • Matting Installation and Construction of Gravel Access Roads in Brownville near Star School House Road and Bonney Road 

  • Structure Drilling and Concrete Pouring at Structure Locations in Pamelia near NYS Route 37
  • Transmission Line Structure Installation in Pamelia near NYS Route 37
  • Matting in Pamelia near NYS Route 37 and Knowslesville Road
  • Gravel Access Roads in Pamelia from NYS Route 37 up to Knowlesville Road
  • Structure Drilling at Structure Locations in Le Ray near Jenkins Road - County Route 16
  • Matting in Pamelia near NYS Route 37, NYS Route 37 and Knowlesville Road, and  Knowlesville Road 
  • Transmission Line Preparation for Wire Pulling and Equipment Transfer to Indian River Substation near US Route 11, and US Route 11 and Jenkins Road - County Route 16
  • Structure Drilling at Structure Locations in Le Ray near Jenkins Road - County Route 16
  • Gravel Access Roads in Pamelia from Parish Road to Knowlesville Road 
  • Transmission Line Structure Installation in Le Ray from US Route 11 and Jenkins Road - County Route 16 and Jenkins Road - County Route 16
  • Structure Drilling at Structure Locations in Le Ray near Jenkins Road - County Route 16, followed by Base Setting
  • Foundation Pouring for Structure Location in Le Ray near US Route 11 and Jenkins Road (County Route 16)
  • Installation of Galvanized Steel Poles at Structure Locations in Le Ray
  • Drilling at Indian River Substation in Le Ray off Rogers Road
  • Underground Foundation Construction at new North Watertown Substation Site in Brownville near Vaadi Road and NYS Route 12
  • Foundation Pouring for Structure Location in Le Ray near US Route 11 and Jenkins Road (County Route 16)
  • Materials and equipment will be transported via trucks to matted areas between Indian River Substation in Le Ray and Waddingham Road, near NYS Route 37 in Pamelia
  • Structure Drilling at Structure Locations in Le Ray near US Route 11
  • Foundation Pouring for Structure Location in Le Ray near US Route 11
  • Materials and equipment will be transported via trucks to matted areas between Indian River Substation in Le Ray and Waddingham Road, near NYS Route 37 in Pamelia
  • Foundation Pouring for Structure Location in Le Ray near US Route 11
  • Structure Drilling at Structure Locations in Le Ray near US Route 11
  • Materials and equipment will be transported via trucks to matted areas between Indian River Substation in Le Ray and Waddingham Road, near NYS Route 37 in Pamelia

2024

  • No Work Tentatively Scheduled this Week
  • No Work Scheduled this Week
  • Construction of Access Road off of Parish Road (near Parish Cemetery)
  • Clearing and Matting along the Project Corridor from NYS Route 37 to Waddingham Road in Pamelia
  • Structure Drilling at Substation in Le Ray near US Route 11