Skip to main content

Construction Schedule

2023

Last week our team continued work on the station upgrade on 62nd Street and 15th Avenue. 

*The week of 6/5 neighbors can expect to see:

  • Continued infrastructure installation on 62nd Street and 15th Avenue from 3:00 pm to midnight
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

Last week our team completed preliminary work on the Bensonhurst project and began work on the station upgrade on 62nd Street and 15th Avenue. Please note that there will not be work on Monday, May 29.

*The week of 5/29 neighbors can expect to see:

  • Continued infrastructure installation on 62nd Street and 15th Avenue from 3:00 pm to midnight
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary

 

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email ddress box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

 

*Please note, due to the complexities of outdoor construction, schedule is subject to change.

Last week our team continued work at the various pit locations associated with this project.

*The week of 5/22 neighbors can expect to see:

  • Daytime work on Monday 5/22 at the pits associated with this project
  • Evening work starting Tuesday 5/23 on 62nd Street and 15th Avenue
  • Once evening hours are resumed, they will remain in place for the bulk of the project
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

Last week our team continued work at the various pit locations associated with this project.

*The week of 5/15 neighbors can expect to see:

  • Continued daytime work at the pits associated with this project
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary
 

Please feel free to reach out to our project specific outreach phone line 1-929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

 

*Please note, due to the complexities of outdoor construction, schedule is subject to change.

Last week our team continued work at the various pit locations associated with this project.

*The week of 5/8 neighbors can expect to see:

  • Continued component installation at the pits associated with this project
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

Last week our team began excavations on 15th Avenue between 62nd Street and 63rd Street.

 *The week of 5/1 neighbors can expect to see:

  • Continued work at the remote pits associated with this project
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary
 

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

Last week our team continued remote excavations for the Bensonhurst project. Please note working hours are from 3pm to 11:30 pm Monday-Friday.

*The week of 4/24 neighbors can expect to see:

  • Excavations on 15th Avenue around 61st Street, 62nd Street and 63rd Street
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary
 

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.

Thank you for your interest in the Bensonhurst Regulator Station Refurbishment Project. Check back for weekly construction updates.

The week of 4/17 neighbors can expect to see:

  • Excavation on 62nd Street between 19th Avenue and 20th Avenue
  • Excavation on 15th Avenue between 57th Street and 58th Street
  • There will be traffic and parking changes near active work zones. Our crews will have flaggers present to redirect traffic as necessary

Please feel free to reach out to our project specific outreach phone line 929-322-0143 or our email address box.brooklyn@nationalgrid.com with any questions, concerns, and comments.