News and Updates
2026
The neighborhood can expect:
- Crews on-site 24/7 at location 2&3, Marguerite Avenue and Makofske Avenue in Elmont, and Roosevelt Avenue and Tulip Avenue in Franklin Square, as well as charge points 6-10:
- Arthur Avenue and Press Street
- Landau Avenue and Adams Street
- Eweler Avenue and Schenck Boulevard
- Fairmount Boulevard and New Hyde Park Road
- Princeton Street and Edgemere Road
The neighborhood can expect:
- Crews on-site 24/7 at location 3, Roosevelt Avenue and Tulip Avenue in Franklin Square, as well as charge points 8-10:
- Eweler Avenue and Schenck Boulevard
- Fairmount Boulevard and New Hyde Park Road
- Princeton Street and Edgemere Road
The neighborhood can expect:
- Crew activities at locations 1&2: Dutch Broadway and Ridge Road and Makofske Avenue and Marguerite Avenue as well as 24/7 operations at charging locations 2-8:
- Renfrew Avenue and First Street
- Belmont Avenue and Elmont Road
- Elmont Road and Joan Court
- Arthur Avenue and Press Street
- Landau Avenue and Adams Street
- Eweler Avenue and Schenck Boulevard
The neighborhood can expect:
- Excavations for the launch locations of maintenance device at the below locations:
-
Location 1: Dutch Broadway & Ridge Road in Elmont, NY
-
Location 2: Makofske Avenue & Marguerite Avenue in Elmont, NY
-
Location 3: Roosevelt Avenue between Benmore Avenue and Tulip Avenue in South Floral Park, NY.
-
The neighborhood can expect:
- Cleaning of 9 charge points along the project route and performing x-rays of these points in preparation for maintenance work. We anticipate this taking 3-6 days to complete