News and Updates
2025
- Continued excavations within the parking lot of Lake Shore Plaza.
For your safety please do not enter work zones and be mindful of traffic cones and signage.
Please note: our crews will not be working the holidays 12/24-12/25 and 12/31-12/1.
- Continued excavations within the parking lot of Lake Shore Plaza.
For your safety please do not enter work zones and be mindful of traffic cones and signage.
Please note: our crews will not be working the holidays 12/24-12/25 and 12/31-12/1.
- Continued excavations within the parking lot of Lake Shore Plaza.
- Crane on-site Thursday, 12/18/2025, to install upgraded infrastructure.
For your safety please do not enter work zones and be mindful of traffic cones and signage.
- Excavations within the parking lot of Lake Shore Plaza.
- Installation of infrastructure.
For your safety please do not enter work zones and be mindful of traffic cones and signage.
- Continuing to work on test holes within the sidewalk and roadway on Cenacle Road.
- Preparing to build excavations for install on Cenacle Road.
- Crews working on test holes within the sidewalk and roadway on Cenacle Road.
- Crews begin excavating on Cenacle Road and within the northeast corner of Lake Shore Plaza.
- Wrapping up civil work and preparing for excavations on Cenacle Road this Monday, 11/17/25.
- Excavations and use of a vacuum truck.
- Civil concrete/fence work
- Excavations and use of a vacuum truck.
- Civil concrete/fence work.
- Crews mobilizing materials to the site.
- Excavations and use of a vacuum truck.