Project Schedule

  • Start of Construction - March 12, 2026
  • Article VII Certificate approved – October 16, 2025
  • Environmental Management and Construction Plan (EM&CP) approved – October 16, 2025
  • Environmental Management and Construction Plan (EM&CP) filed – July 31, 2025
  • Public Statement Hearing – September 18, 2024
  • Article VII Application Deemed Complete – June 25, 2024
  • Article VII Application Filed – February 27, 2024

July 29, 2026

  •  Continued installation and maintenance of erosion and sediment control measures throughout the project area.
  •  Ongoing duct bank excavation, conduit installation, concrete encasement, and backfilling activities.
  •  Construction of underground vault structures and preparation for railroad crossing installation activities.

July 15, 2026

  • Continued installation of erosion and sediment control measures as needed throughout the project area.
  • Ongoing duct bank excavation, conduit installation, and concrete encasement activities.
  • Construction of underground vault structures and associated backfilling operations.

July 1, 2026

  • Mobilization of construction crews, equipment, and materials for project construction activities.
  • Survey activities and installation of erosion and sediment control measures along the project corridor.
  • Initiation of duct bank excavation, conduit installation, and related civil construction work.

March 12, 2026

  • Construction start.
  • Mobilization of crews and equipment.
  • Initial tree and vegetation removal.