Project Schedule
- Start of Construction - March 12, 2026
- Article VII Certificate approved – October 16, 2025
- Environmental Management and Construction Plan (EM&CP) approved – October 16, 2025
- Environmental Management and Construction Plan (EM&CP) filed – July 31, 2025
- Public Statement Hearing – September 18, 2024
- Article VII Application Deemed Complete – June 25, 2024
- Article VII Application Filed – February 27, 2024
July 29, 2026
- Continued installation and maintenance of erosion and sediment control measures throughout the project area.
- Ongoing duct bank excavation, conduit installation, concrete encasement, and backfilling activities.
- Construction of underground vault structures and preparation for railroad crossing installation activities.
July 15, 2026
- Continued installation of erosion and sediment control measures as needed throughout the project area.
- Ongoing duct bank excavation, conduit installation, and concrete encasement activities.
- Construction of underground vault structures and associated backfilling operations.
July 1, 2026
- Mobilization of construction crews, equipment, and materials for project construction activities.
- Survey activities and installation of erosion and sediment control measures along the project corridor.
- Initiation of duct bank excavation, conduit installation, and related civil construction work.
March 12, 2026
- Construction start.
- Mobilization of crews and equipment.
- Initial tree and vegetation removal.