Project Schedule

The schedule is high-level and subject to change. It will be updated as the project progresses.

Milestone Date

Field Investigations & Design

Complete

Article VII Application Submission

January 31, 2025

Article VII Certificate Approval

July 14, 2025

Construction Start

March 2026

Estimated Construction Completion

September 2026

Estimated Final Restoration

October 2027