News and Updates

2023

Last week our crews continued the retirement of the old NL-25 regulator station on Dutch Broadway, including the removal of about 66 feet of pipe. 

This week neighbors can expect to see:

  • Continued removal of retired infrastructure and materials.
  • Electric disconnection of the old regulator station by PSEG.
  • Continued restoration of the work zone, including sidewalk paving on Dutch Broadway.

*Due to the complexity of outside construction, schedule is subject to change.

Ridge Road and Dutch Broadway will be restored to Town of Hempstead standards once work is complete.

Last week our crews continued removal of retired infrastructure from the old NL-25 regulator station, and continued restoration of the work zone on Dutch Broadway and Ridge Road. 

This week neighbors can expect to see:

  • Continued removal of retired infrastructure and materials.
  • Continued restoration of the site on Dutch Broadway and site on Ridge Road.

 

*Due to the complexity of outside construction, schedule is subject to change.

Ridge Road and Dutch Broadway will be restored to Town of Hempstead standards once work is complete.

Last week our crews removed retired infrastructure from the old NL-25 regulator station, backfilled excavations, and temporarily restored Dutch Broadway. 

This week neighbors can expect to see:

  • Continued removal of retired infrastructure and materials.
  • Continued restoration of the site on Dutch Broadway and site on Ridge Road

*Due to the complexity of outside construction, schedule is subject to change.

Ridge Road and Dutch Broadway will be restored to Town of Hempstead standards once work is complete.

Last week our crews returned to the site to begin removal of the old NL-25 regulator station, including excavation of the grass area along the south side of Dutch Broadway, between Ridge Road and Elmont Road.

This week neighbors can expect to see:

  • Continued excavation and backfilling on the south side of Dutch Broadway.
  • Removal of existing regulator station and associated materials.
  • The right-hand, eastbound lane of Dutch Broadway closed to traffic, and sidewalk closed to pedestrians between Ridge Road and Elmont Road.
  • Possible restoration work in the grass on Ridge Road.
 

*Due to the complexity of outside construction, schedule is subject to change.

Ridge Road and Dutch Broadway will be restored to Town of Hempstead standards once work is complete.

No work took place on-site last week.

This week our crews will be returning to the site to begin demolition of the old NL-25 regulator station, including excavation of the grass area directly to the south of Dutch Broadway, near the intersection of Ridge Road. This work is expected to be completed in fall 2023.

Ridge Road and Dutch Broadway will be restored to Town of Hempstead standards once work is complete.

*Due to complexity of outdoor construction, schedule is subject to change.

Last week our Instrumentation & Regulation team performed underground vault work on Ridge Road and placed the new NL-25 regulator station in service. Our construction team also completed roadway and sidewalk excavations on the south side of Dutch Broadway, across from the intersection of Ridge Road. These excavations have been secured and plated, and Dutch Broadway is now fully open to traffic.

No work is expected this week, however, our team will be returning to the site on or about 5/8/23 to begin demolition of the old NL-25 regulator station, including excavation of the grass area directly to the south of Dutch Broadway, near the intersection of Ridge Road. This work is expected to be completed in fall 2023 and will not affect the roadway. 

Ridge Road and Dutch Broadway will be restored to Town of Hempstead standards once work is complete.

*Please note, due to complexities of outdoor construction, schedule is subject to change. 

Last week our construction team began roadway and sidewalk excavations on the south side of Dutch Broadway, across from the intersection of Ridge Road. The right-hand, eastbound lane of Dutch Broadway will be closed during working hours near the intersection of Ridge Road, until approximately April 28th.  Dutch Broadway will be secured, plated and fully open to traffic during non-work hours. 

Our Instrumentation and Regulation team also performed underground vault work on Ridge Road.

This week neighbors can expect to see:

  • Continued excavation and backfilling on the south side of Dutch Broadway. 
  • Continued vault work on Ridge Road by our Instrumentation & Regulation team.

 

Demolition work in the grass area adjacent to Dutch Broadway will begin in May 2023, and is expected to be completed in June 2023. This work will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

*Please note, due to complexities of outdoor construction, schedule is subject to change

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road.

This week neighbors can expect roadway and sidewalk excavation on Dutch Broadway including lane closures. The right-hand eastbound lane of Dutch Broadway will be closed near the intersection of Ridge Road. Excavation will begin on April 20th and last approximately one week. Dutch Broadway will be secured, plated and fully open to traffic during non-work hours. 

Demolition work in the grass area adjacent to Dutch Broadway will begin in May, and is expected to be completed in June. This work will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

 

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road.

This week neighbors can expect to see:

  • Continued vault work by National Grid’s Instrumentation & Regulation team.

Work adjacent to Dutch Broadway will resume in mid-April. This work will take place in the grass easement and will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road.

This week neighbors can expect to see:

  • Continued vault work by National Grid’s Instrumentation & Regulation team.

Work adjacent to Dutch Broadway will resume in mid-April. This work will take place in the grass easement and will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road.

This week neighbors can expect to see:

  • Continued vault work by National Grid’s Instrumentation & Regulation team.

Work adjacent to Dutch Broadway will resume in mid-April. This work will take place in the grass easement and will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road

This week neighbors can expect to see:

  • Continued vault work by National Grid’s Instrumentation & Regulation team.
 

Work adjacent to Dutch Broadway will resume in mid-April. This work will take place in the grass easement and will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road

This week neighbors can expect to see:

  • Continued vault work by National Grid’s Instrumentation & Regulation team.
 

Work adjacent to Dutch Broadway will resume in mid-April. This work will take place in the grass easement and will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week National Grid’s Instrumentation & Regulation team performed vault work on Ridge Road

This week neighbors can expect to see:

  • Continued vault work by National Grid’s Instrumentation & Regulation team.
 

Work adjacent to Dutch Broadway will resume in mid-March. This work will take place in the grass easement and will not affect the roadway. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed last week.

This week neighbors can expect to see:

  • Vault work by National Grid’s Instrumentation & Regulation team.

 

Work adjacent Dutch Broadway will resume in March. This work will take place in the grass easement and will not affect the roadway.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed last week and no work is scheduled for this week. National Grid's Instrumentation and Regulation Team will be on site at Ridge Road working within vaults beginning February 27th. 

Excavation adjacent to Dutch Broadway will resume in March. This work will take place in the grass easement and will not affect the roadway.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed last week.

This week neighbors can expect to see:

  • Vault work by National Grid’s Instrumentation & Regulation team.

Work adjacent Dutch Broadway will resume in March. This work will take place in the grass easement and will not affect the roadway.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed last week.

This week neighbors can expect to see:

  • Possible vault work by National Grid’s Instrumentation & Regulation team.
     

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed this week.

This week neighbors can expect to see:

  • Possible vault work by National Grid’s Instrumentation & Regulation team.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed this week.

This week neighbors can expect to see:

  • Possible vault work by National Grid’s Instrumentation & Regulation team.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work was performed this week.

No work is scheduled for next week.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

2022

No work was performed this week.

No work is scheduled for next week.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work took place last week.

Next week, residents can expect work by National Grid’s Instrumentation and Regulation team to get the station prepared for gas-in.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic, as necessary.

*Construction schedule is subject to change.

Last week our construction team completed restoration of curbs and sidewalks on Ridge Road. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic, as necessary.

No work is scheduled for this week.

*Construction schedule is subject to change.

Last week our construction team wrapped underground infrastructure, restored curbs and sidewalks on Ridge Road and continued backfilling on Ridge Road and Dutch Broadway, in addition to electrical work by PSEG and work by National Grid’s Instrumentation & Regulation Team.

This week neighbors can expect to see: 

  • Continued work by National Grid’s Instrumentation & Regulation Team.
  • Restoration of Ridge Road and Dutch Broadway.

*Construction schedule is subject to change.

Last week our construction team completed wrapping of underground infrastructure, flange installations, backfilling on Ridge Road and Dutch Broadway, restoration of curbs and sidewalks, and work by National Grid's Instrumentation and Regulation Team. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Ridge Road. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Continued work by National Grid's Instrumentation and Regulation Team.
  • Continued restoration of curbs and sidewalks on Ridge Road.
  • Electrical work by PSEG. Restoration of curbs and sidewalks.

*Construction schedule is subject to change.

Last week our construction team installed vault ladders, placed underground infrastructure in service, and continued backfilling on Ridge Road and Dutch Broadway. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Ridge Road. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Wrapping of underground infrastructure.
  • Flange installations.
  • Work by National Grid’s Instrumentation & Regulation Team.
  • Continued backfilling on Ridge Rd and Dutch Broadway.
  • Restoration of curbs and sidewalks.

*Construction schedule is subject to change.

Last week our construction team installed cabinets on Dutch Broadway, installed vent poles on Ridge Road, and continued excavation and backfilling on Dutch Broadway and Ridge Road. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Ridge Road. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Installing vault ladders.
  • Placing underground infrastructure in service.
  • Continued backfilling on Ridge Rd and Dutch Broadway.

*Construction schedule is subject to change.

Last week our construction team continued excavation and the installation of distribution infrastructure on Dutch Broadway, performed pressure testing, installed vault lids, backfilled excavations, and installed equipment on Ridge Road. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Cabinet installation on Dutch Broadway.
  • Vent Pole installation on Ridge Road.
  • Continued backfilling on Ridge Road and Dutch Broadway.

Last week our construction team continued the excavation and installation of distribution infrastructure on Dutch Broadway, as well as backfilling of excavations, and installation of equipment on Ridge Road. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Continued excavation, backfilling, and installation of distribution infrastructure on Dutch Broadway and Ridge Road.
  • Seating of pedestal bases, vault work, and preparing new infrastructure to be put in service.

*Construction schedule is subject to change.

Last week our construction team continued the excavation and installation of distribution infrastructure on Dutch Broadway and installed equipment on Ridge Road. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Continued excavation and installation of distribution infrastructure on Dutch Broadway.
  • Installation of vault lids, backfilling, and prefabrication of the vent infrastructure on Ridge Road.

 

*Construction schedule is subject to change.

Last week our construction team completed pressure testing, excavation across Dutch Broadway toward Ridge Road, and continued backfilling of existing excavations on Dutch Broadway. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic, as necessary.

This week neighbors can expect to see: 

  • Excavation and installation of distribution infrastructure on Dutch Broadway.
  • Installation of equipment on Ridge Road.

 

*Construction schedule is subject to change.

Last week our construction team performed excavation and backfilling along Dutch Broadway, welding, sealing and painting of underground infrastructure, and conduit work. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see 

  • Pressure testing
  • Possible Verizon infrastructure work
  • Possible excavation across Dutch Broadway toward Ridge Road
  • Continued backfilling of existing excavations on Dutch Broadway

Last week our construction team performed excavation and backfilling, welding, and sealing and painting of underground infrastructure along Dutch Broadway. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see 

  •  Continued welding and underground infrastructure connection
  • Possible Verizon infrastructure work
  • Possible excavation across Dutch Broadway toward Ridge Road
  • Continued backfilling of existing excavations on Dutch Broadway

*Construction schedule subject to change

Last week our construction team performed underground valve work, excavating on Dutch Broadway and backfilling of excavation pits on Ridge Road. Please note that traffic patterns and parking availability will be affected near active work areas. Expect lane closures on Dutch Broadway. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see: 

  • Continued excavation and backfilling along Dutch Broadway
  • Welding
  • Sealing and painting of underground infrastructure
  • Possible Verizon infrastructure work

*Construction Schedule is subject to change

Last week our construction team performed pressure testing, backfilling of excavation pits and welding. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Excavations
  • Backfilling of excavation
  • Underground valve work
     

*Construction schedule is subject to change

Last week our construction team performed pressure testing, underground vault work and welding. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling of excavations
  • Underground vault work
  • Continued pressure testing

*Construction schedule is subject to change

Last week our construction team performed pressure testing. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see

  • Underground vault work
  • Welding

*Construction schedule is subject to change

Last week our construction team continued underground maintenance work including the installation of control lines.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Quality assurance testing of the infrastructure

Last week our construction team performed excavations and mechanical repairs to underground infrastructure.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Welding and additional underground installation work
  • Pressure testing on or about Monday 8/29 and Tuesday 8/30, beginning at 6:00 a.m.
  • Sunday - No work scheduled
  • Monday - Friday - Excavation mechanical repairs - Hydro test scheduled around Thursday and Friday
  • Saturday - Possible work scheduled
     

 Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding and mechanical repairs
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding
  • Saturday - No work scheduled
     

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding 
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Holiday - No work scheduled
  • Tuesday - Friday - Welding inside vaults
  • Saturday - No work scheduled
     

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding / Fabricating inside vaults
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding / Fabricating inside vaults
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding / Fabricating inside vaults
  • Saturday - No work scheduled

 

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding / Fabricating inside vaults 
  • Saturday - No work scheduled

 

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - No work scheduled - Memorial Day
  • Tuesday - Friday - Welding / Fabricating inside vaults
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Welding / Fabricating inside vaults
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Thursday - Preparing new vault pits
  • Friday - Setting vaults with/crane and temporary road closures/traffic detours
  • Saturday - No work scheduled

Please note: Schedule is subject to change

  • Sunday - No work scheduled
  • Monday - Friday - Excavation on Ridge Road
  • Saturday - Now work scheduled

 

Please note: Schedule is subject to change