Skip to main content

News and Updates

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

ALL BUSINESSES ON RHINE AVENUE, RICHMOND ROAD, DEKALB STREET, AND NARROWS ROAD N ARE OPEN DURING CONSTRUCTION.  THERE ARE TRAFFIC FLAGGERS ON-SITE TO ASSIST VEHICULAR AND PEDESTRIAN TRAFFIC AS NECESSARY.

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

2024

Last week multiple crews continued excavating and installing infrastructure on Narrows Road N between Richmond Road and Little Clove Road and on Rhine Avenue and Dekalb Street. Crews began excavating for the remote openings on Little Clove Road between Bristol Avenue and Northern Boulevard during daytime hours. 

This week neighbors can expect to see:

  • Continued work during the daytime to excavate on Little Clove Road between Bristol Avenue and Northern Boulevard for our remote openings. 
  • Continued nighttime excavations on Rhine Avenue & Dekalb Street.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts on Dekalb Street, Rhine Avenue and the Staten Island Expressway Service Road, Narrows Road N, Little Clove Road, and Richmond Road.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.

Last week multiple crews continued backfilling excavations on Narrows Road N between Richmond Road and Little Clove Road and on Rhine Avenue and Dekalb Street. 

This week neighbors can expect to see:

  • On 05/12/2024, crew will be working during the daytime to excavate on Little Clove Road between Bristol Avenue and Northern Boulevard for our remote openings. 
  • Continued nighttime excavations on Rhine Avenue & Dekalb Street.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts on Dekalb Street, Rhine Avenue and the Staten Island Expressway Service Road, Narrows Road N, Little Clove Road, and Richmond Road.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.

Last week multiple crews continued backfilling excavations on Narrows Road N between Richmond Road and Little Clove Road and at Rhine Avenue and Narrows Road N. Our crews also performed excavations on Rhine Avenue.  

This week neighbors can expect to see:

  • Continued excavations and backfilling on Rhine Avenue.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts on Dekalb Street, Rhine Avenue and the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.

Road closures for excavation on Dekalb Street and excavations on Rhine Avenue during construction hours. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.

Last week multiple crews continued installing upgraded infrastructure and backfilling excavations on Narrows Road N between Richmond Road and Little Clove Road and at Rhine Avenue and Narrows Road N.

This week neighbors can expect to see:

  • Excavation on Dekalb Street beginning Sunday night, 4/28. Work hours 9PM to 5AM.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts on Dekalb Street, Rhine Avenue and the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road.
  • Excavations on Rhine Avenue.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.
     

Road closures for excavation on Dekalb Street and excavations on Rhine Avenue during construction hours. including this Sunday, 4/28. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM. (and Sunday 4/28)*

Last week multiple crews continued installing upgraded infrastructure and backfilling excavations on Narrows Road N between Richmond Road and Little Clove Road and at Rhine Avenue and Narrows Road N.

This week neighbors can expect to see:

  • Installation of infrastructure on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Excavations on Rhine Avenue.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.

Road closures for welding activities and material mobilization on Dekalb Street and excavations on Rhine Avenue during construction hours. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*

Last week multiple crews continued installing upgraded infrastructure and backfilling excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue installing infrastructure and backfilling excavations on Narrows Road N heading west towards Little Clove Road. There will also be a second crew excavating on Rhine Avenue and welding and creating boxes on Dekalb Street. Both Rhine Avenue and Dekalb Street will be closed during construction hours.

This week neighbors can expect to see:

  • Road closures for welding activities and material mobilization on Dekalb Street and excavations on Rhine Avenue during construction hours. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  •  Installation of infrastructure on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Excavations on Rhine Avenue.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.
     

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week multiple crews continued installing upgraded infrastructure and backfilling excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue installing infrastructure and backfilling excavations on Narrows Road N heading west towards Little Clove Road. There will also be a second crew excavating on Rhine Avenue and welding and creating boxes on Dekalb Street. Both Rhine Avenue and Dekalb Street will be closed during construction hours.

This week neighbors can expect to see:

  • Road closures for welding activities and material mobilization on Dekalb Street and excavations on Rhine Avenue during construction hours. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  •  Installation of infrastructure on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Excavations on Rhine Avenue.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.
     
 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week multiple crews continued installing upgraded infrastructure and backfilling excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue installing infrastructure and backfilling excavations on Narrows Road N heading west towards Little Clove Road. There will also be a second crew excavating on Rhine Avenue and welding and creating boxes on Dekalb Street. Both Rhine Avenue and Dekalb Street will be closed during construction hours.

This week neighbors can expect to see:

  • Road closures for welding activities and material mobilization on Dekalb Street and excavations on Rhine Avenue during construction hours. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  •  Installation of infrastructure on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Excavations on Rhine Avenue.
  • Welding and boxing on Dekalb Street for Rhine Avenue excavations.
  • Material mobilization activities within the laydown yard located on Ontario Avenue.

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week multiple crews continued installing upgraded infrastructure and backfilling excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue installing infrastructure and backfilling excavations on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Temporary road closures for night work and material mobilization on Dekalb Street and Rhine Avenue during mobilization of materials. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  •  Installation of infrastructure on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Material mobilization activities within the laydown yard located on Ontario Ave.
  • Staging and material storage activities on Dekalb Street and Rhine Avenue during construction hours, which may require periodic road closures. 

 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week multiple crews continued excavating, installing upgraded infrastructure, and backfilling excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue installing infrastructure and backfilling excavations on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Temporary road closures for night work and material mobilization on Dekalb Street and Rhine Avenue during mobilization of materials. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavation of the roadway and Installation of infrastructure on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Material mobilization activities within the laydown yard located on Ontario Ave.
  • Staging and material storage activities on Dekalb Street and Rhine Avenue during construction hours, which may require periodic road closures. 
 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week multiple crews continued excavating and installing upgraded infrastructure between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will begin backfilling some excavations on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Temporary road closures for night work and material mobilization on Dekalb Street and Rhine Avenue during mobilization of materials. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of some excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Material mobilization activities within the laydown yard located on Ontario Ave.
  • Staging and material storage activities on Dekalb Street and Rhine Avenue during construction hours.
 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week multiple crews continued excavating and installing upgraded infrastructure between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will begin backfilling some excavations on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Temporary road closures for night work and material mobilization on Dekalb Street and Rhine Avenue during mobilization of materials. Night work and temporary road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Backfilling of some excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Material mobilization activities within the laydown yard located on Ontario Ave.
  • Staging and material storage activities on Dekalb Street and Rhine Avenue during construction hours.
     
 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Temporary road closures for night work and material mobilization on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Night work welding activities within the laydown yard located on Ontario Ave.
  • Welding and material storage activities on Dekalb Street and Rhine Avenue during construction hours.

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Richmond Road and Little Clove Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Road closures for night work and material mobilization on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N between Richmond Road and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Night work welding activities within the laydown yard located on Ontario Ave.
  • Welding and material storage activities on Dekalb Street and Rhine Avenue during construction hours.
 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Rhine Avenue and Richmond Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Road closures for night work and material mobilization on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N between Rhine Avenue and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Night work welding activities within the laydown yard located on Ontario Ave.
  • Welding and material storage activities on Dekalb Street and Rhine Avenue during construction hours.
 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Rhine Avenue and Richmond Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Road closures for night work and material mobilization on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N between Rhine Avenue and Little Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Night work welding activities within the laydown yard located on Ontario Ave.
  • Welding and material storage activities on Dekalb Street and Rhine Avenue during construction hours.

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Rhine Avenue and Richmond Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N heading west towards Little Clove Road.

This week neighbors can expect to see:

  • Road closures for night work on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Miscellaneous excavations on Narrows Road N between Rhine Avenue and Clove Road.
  • Excavations on Narrows Road N.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Night work welding activities within the laydown yard located on Ontario Ave.
     

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Rhine Avenue and Richmond Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N.

This week neighbors can expect to see:

  • Road closures for night work on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Miscellaneous excavations on Narrows Road N between Rhine Avenue and Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
  • Night work welding activities within the laydown yard located on Ontario Ave.
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

 

ALL BUSINESSES ON RHINE AVENUE, RICHMOND ROAD, DEKALB STREET, AND NARROWS ROAD N ARE OPEN DURING CONSTRUCTION.  THERE ARE TRAFFIC FLAGGERS ON-SITE TO ASSIST VEHICULAR AND PEDESTRIAN TRAFFIC AS NECESSARY.

 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews continued excavations between Rhine Avenue and Richmond Road on Narrows Road N. This week our crews will continue to excavate and install infrastructure on Narrows Road N.

This week neighbors can expect to see:

  • Road closures for night work on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Miscellaneous excavations on Narrows Road N between Rhine Avenue and Clove Road.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road N, and Richmond Road. 
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

 

ALL BUSINESSES ON RHINE AVENUE, RICHMOND ROAD, DEKALB STREET, AND NARROWS ROAD N ARE OPEN DURING CONSTRUCTION.  THERE ARE TRAFFIC FLAGGERS ON-SITE TO ASSIST VEHICULAR AND PEDESTRIAN TRAFFIC AS NECESSARY.

 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week our crews resumed construction activities near Richmond Road, Dekalb Street, Rhine Avenue, and Narrows Road N. Prefabrication activities resumed in our laydown yard on Ontario Avenue during daytime hours. 

This week neighbors can expect to see:

  • Road closures for night work excavations on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N at night between Rhine Avenue and Richmond Road.
  • Miscellaneous excavations on Narrows Road N between Rhine Avenue and Clove Road.
  • Prefabrication activities at our laydown yard located on Ontario Avenue during daytime hours.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and road closures on Dekalb Street and Rhine Avenue.
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

 

ALL BUSINESSES ON RHINE AVENUE, RICHMOND ROAD, DEKALB STREET, AND NARROWS ROAD N ARE OPEN DURING CONSTRUCTION.  THERE ARE TRAFFIC FLAGGERS ON-SITE TO ASSIST VEHICULAR AND PEDESTRIAN TRAFFIC AS NECESSARY.

 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

2023

Construction activities will be paused for the holidays from Friday, December 15th, 2023, to Monday, January 01st, 2024.

*Schedule is subject to change due to project-specific activities.

 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

 

Within the last two weeks our crews paused construction activities for the holidays. Construction activities are scheduled to resume Tuesday, January 02, 2024.  

This week neighbors can expect to see:

  • Road closures for night work excavations on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Excavations on Narrows Road N at night between Rhine Avenue and Richmond Road.
  • Miscellaneous excavations on Narrows Road N between Rhine Avenue and Clove Road.
  • Prefabrication activities at our laydown yard located on Ontario Avenue during daytime hours.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and road closures on Dekalb Street and Rhine Avenue.
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

 

ALL BUSINESSES ON RHINE AVENUE, RICHMOND ROAD, DEKALB STREET, AND NARROWS ROAD N ARE OPEN DURING CONSTRUCTION.  THERE ARE TRAFFIC FLAGGERS ON-SITE TO ASSIST VEHICULAR AND PEDESTRIAN TRAFFIC AS NECESSARY.

 

*Schedule is subject to change due to project-specific activities and additional traffic/road impacts may be necessary for the use of cranes and other heavy equipment.

Last week, our crews began mobilizing and closed Rhine Avenue from Dekalb Street to Narrows Road N during nightwork. Crews began opening pits for the relocation of additional utilities and performed test pits.

This week neighbors can expect to see:

  • No active construction from Friday, December 15th, 2023, to Monday, January 01st, 2024.
     

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued restoration in the roadway and sidewalks for the installation of new infrastructure on Narrows Road N heading East towards Rhine Avenue. Crews began mobilizing for work on Rhine Avenue.

This week neighbors can expect to see:

  • Road closures for night work excavations on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Continue to backfill open excavations on Narrows Road N.
  • Test pits and excavations on Rhine Avenue.
  • Prefabrication activities at our laydown yard located on Ontario Avenue during daytime hours.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and road closures on Dekalb Street and Rhine Avenue.

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued restoration in the roadway and sidewalks for the installation of new infrastructure on Narrows Road N heading East towards Rhine Avenue.

This week neighbors can expect to see:

  • Road closures for night work excavations on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and road closures on Dekalb Street and Rhine Avenue.
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued restoration activities in the roadway and sidewalks after the installation of new infrastructure on Narrows Road N in front of Sunrise Senior Living and Sunrise Condominiums.

This week neighbors can expect to see:

  • Completed cut and cap activities and continued restoration of the roadway and sidewalks along Narrows Road N moving East towards Rhine Avenue.
  • Beginning road closures for night work on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, Little Clove Road, and road closures on Dekalb Street and Rhine Avenue.
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued excavations in the roadway and sidewalks for the installation of new infrastructure along Narrows Road N. Crews also began tie in activities.

This week neighbors can expect to see:

  • Continued tie in activities along Narrows Road N, including the use of a vac truck, saw cutter, and excavator.
  • Beginning road closures for night work on Dekalb Street and Rhine Avenue. Night work and road closure hours are, Monday through Friday, 9PM to 5AM.*
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, Little Clove Road, and road closures on Dekalb Street and Rhine Avenue.

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued excavations in the roadway and sidewalks for the installation of new infrastructure along Narrows Road N. Crews continued service upgrade work for buildings along the route on Narrows Road N during the daytime hours.

This week neighbors can expect to see:

  • Continued excavations for new infrastructure along Narrows Road N, including the use of a vac truck, saw cutter, and excavator.
  • Daytime work hours for the two building service upgrades along Narrows Road N. Hours are Monday through Friday, 2PM to 10PM*.
  • Begin tie-in activities along Narrows Road N during night hours, Monday through Friday, 9PM to 5PM.*

Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road.

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued excavations in the roadway and sidewalks for the installation of new infrastructure along Narrows Road N. Crews also began service upgrade work for buildings along the route on Narrows Road N during the daytime hours.

This week neighbors can expect to see:

  • Continued excavations for new infrastructure along Narrows Road N, including the use of a vac truck, saw cutter, and excavator.
  • Daytime work hours for the two building service upgrades along Narrows Road N. Hours are Monday through Friday, 2PM to 10PM*.
  • Plating of excavations once work is complete for the night/day.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road.
  • Restoration of the disturbed areas for the service upgrades.
  • Possible tie-in activities.

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued excavations in the roadway and sidewalks for the installation of new infrastructure along Narrows Road N. Crews also began service upgrade work for buildings along the route on Narrows Road N.

This week neighbors can expect to see:

  • Continued excavations for new infrastructure along Narrows Road N, including the use of a vac truck, saw cutter, and excavator.

  • Daytime work hours for the two building service upgrades along Narrows Road N. Hours are Monday through Friday, 2PM to 10PM*. 

  • Plating of excavations once work is complete for the night/day.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road.

 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

 

*Schedule is subject to change due to project-specific activities.

Last week, our crews continued excavations in the roadway and sidewalks for the installation of new infrastructure along Narrows Road N.

This week neighbors can expect to see:

  • Continued excavations along Narrows Road, including the use of a vac truck, saw cutter, and excavator.
  • Plating of excavations once work is complete for the night.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road, beginning at approximately 9PM. 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

Last week, our crews continued excavations in the roadway and sidewalks for the installation of new infrastructure along Narrows Road N.

This week neighbors can expect to see:

  • Continued excavations along Narrows Road, including the use of a vac truck, saw cutter, and excavator.
  • Plating of excavations once work is complete for the night.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road, beginning at approximately 9PM. 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

Last week, our crews began night work, starting with excavations for test holes near the intersection of the Staten Island Expressway Service Road and Narrows Road, as well as excavations in the roadway and/or sidewalk area near Narrows Road and Little Clove Road. 

This week neighbors can expect to see:

  • Continued excavations along Narrows Road, including the use of a vac truck.
  • Plating of excavations once work is complete for the night.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road, beginning at approximately 9PM. 
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

Last week, our crews began night work, starting with excavations for test holes near the intersection of the Staten Island Expressway Service Road and Narrows Road, as well as excavations in the roadway and/or sidewalk area near Narrows Road and Little Clove Road. 

This week neighbors can expect to see:

  • Continued excavations along Narrows Road, including the use of a vac truck.
  • Plating of excavations once work is complete for the night.
  • Continued traffic impacts along the Staten Island Expressway Service Road, Narrows Road, and Little Cove Road, beginning at approximately 9PM. 
 

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

Last week, neighbors can expect test hole excavations to begin, as well as excavations in the roadway and/or sidewalk area near Little Clove Road.

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.

Crews will begin work on Narrows Road N. 

This week neighbors can expect to see:

  • Excavations in the roadway and/or sidewalks near Littel Clove Road.
  • Test hole activities.
     

IMPORTANT INFORMATION:

Please note that traffic patterns and parking availability will be affected near active work areas. Flaggers will be present to redirect traffic, as necessary. There will be noise impacts associated with excavations and other construction activities.