Construction Schedule
Current Work Hours:
Intersection of 130th Street and South Conduit Avenue
- When school is open
- 9:00 am to 2:00 pm, Monday through Friday
3:00 pm to 6:00 pm, Monday through Friday - When school is closed
- 8:00 am to 3:00 pm, Monday through Friday
South Conduit Avenue between 129th Street and 130th Street
- When school is open
- 9:00 am to 2:00 pm, Monday through Friday
3:00 pm to 6:00 pm, Monday through Friday - When school is closed
- 8:00 am to 3:00 pm, Monday through Friday
South Conduit Avenue between 128th Street and 129th Street
- 8:00 am to 3:00 pm, Monday through Friday
Intersection of 129th Street and South Conduit Avenue
- When school is open
- 9:00 am to 2:00 pm, Monday through Friday
3:00 pm to 6:00 pm, Monday through Friday - When school is closed
- 8:00 am to 3:00 pm, Monday through Friday
130th Street between South Conduit Avenue and 150th Avenue
- 9:00 am to 2:00 pm, Monday through Friday
130th Street between 150th Avenue and Old South Road
- 7:00 am to 6:00 pm, Monday through Friday
Old South Road between 128th Street and 130th Street
- 7:00 am to 6:00 pm, Monday through Friday
Project Timeline:
The timeline below is approximate and subject to change. The timeline will be updated as construction progresses. Please note that this project is multi-year with intermittent work. This schedule reflects planned construction starting in 2024.
Phase I (Brooklyn)
Milestone | Approximate Date |
---|---|
Construction Start | March 2024 |
Final Restoration Start | September 2024 |
Construction End | October 2024 |
Phase II (Jamaica Bay East)
Milestone | Approximate Date |
---|---|
Construction Start | November 2024 |
Final Restoration Start | TBD |
Construction End | TBD |