Construction Schedule
Phase 1: Metropolitan Avenue
We anticipate occupying 2-3 blocks at a time for approximately 4-6 weeks. Please note weather and other unforeseen issues could change this timeline.
| Milestone | Approximate Date |
|---|---|
| Construction Start: Phase 1 | July 14,2026 |
| Current work zone | North side of Metropolitan Avenue between Ascan Avenue to 72nd Avenue. |
| Phase 1 Pause (Holiday Embargo) | November 15,2026 |
| Phase 1 Resumes (post-Holiday Embargo) | Mid-January 2027 |
| Tie in Activities & Final Restoration | Late-Spring 2027 |
Phase 2: Gate Station
| Milestone | Approximate Date |
|---|---|
| Phase 2 Construction Start | 2029 |
| Phase 2 Construction Complete | 2031 |
| Project In-service Date | 2032 |