2026

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue. 
  • Backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue and at the intersection of Ascan Avenue and Metropolitan Avenue.
  • Backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and 72nd Avenue and at the intersection of Ascan Avenue and Metropolitan Avenue.
  • Backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Saw cutting and asphalt preparations between 72nd Road and Continental Avenue from August 3, 2026 through August 11, 2026.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities: 

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between Ascan Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued Vacuum excavations and installation of infrastructure on Metropolitan Avenue between Ascan Avenue and 72nd Avenue. Please see the project map for updates.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue.

The neighborhood can expect the following activities:

  • Continued Vacuum excavations on Metropolitan Avenue between Ascan Avenue and 72nd Road.
  • Installation of infrastructure.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.

The neighborhood can expect the following activities:

  • Mobilization on Metropolitan Avenue and Ascan Avenue.
  • Vacuum excavations on Metropolitan Avenue and Ascan Avenue.

For your safety, please do not enter work zones and be mindful of traffic cones and signage. 

work zone

2025

  • Continued inspections and test hole excavations within our property on 70th Drive and Metropolitan Avenue
  • Temporary and then final restoration of the site
  • Crews will be conducting inspections within our property on 70th Drive and Metropolitan Avenue