The neighborhood can expect the following activities:

  • Wrapping and testing of infrastructure with our property at 100-32 Metropolitan Avenue.
  • Backfilling of open excavations within our property.

Holiday embargo in effect from November 15,2026 through January 02,2026on Metropolitan Avenue. Work on Metropolitan Avenue to resume post-holiday embargo.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued activities within our yard at 100-32 Metropolitan Avenue.
  • No work 11/26/26-11/29/26.

Holiday embargo in effect from November 15,2026 through January 02,2026on Metropolitan Avenue. Work on Metropolitan Avenue to resume post-holiday embargo.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued activities within our yard at 100-32 Metropolitan Avenue.
  • Crane operations are tentatively planned for Friday, November 20th, 2026. There will be temporary road closures on Metropolitan Avenue and 70th Drive during work hours 9AM to 3PM.*
     

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued installations on Metropolitan Avenue between Continental Avenue and 70th Drive.
  • Activities within our yard at 100-32 Metropolitan Avenue.
  • NIGHT RESTORATION on Tuesday November 10,2026: on Metropolitan Avenue between Continental Avenue and 70th Drive. 
  • Crane operations are tentatively planned for Thursday, November 12,2026. There will be temporary road closures on Metropolitan Avenue and 70th Drive.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between Continental Avenue and 70th Drive.
  • Prefabrication and other activities within our yard at 100-32 Metropolitan Avenue.
  • Backfilling and temporary restoration of sections on Metropolitan Avenue between Continental Avenue and 70th Drive.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Weekend work:

  • Sunday 11/01/26.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Night work paving 10/29/26 10PM to 5AM on Metropolitan Avenue from Continental Avenue to 70th Drive.
  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 71st Drive and 70th Drive.
  • Prefabrication and other activities within our yard at 100-32 Metropolitan Avenue.
  • Backfilling and temporary restoration of sections on Metropolitan Avenue between 71st Drive and Continental Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Upcoming weekend work:

  • Sunday 11/01/26.

 

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 71st Drive and 70th Drive.
  • Prefabrication and other activities within our yard at 100-32 Metropolitan Avenue.
  • Backfilling and temporary restoration of sections on Metropolitan Avenue between 71st Drive and Continental Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.
     

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 71st Drive and Continental Avenue. 
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Backfilling of sections on Metropolitan Avenue between 71st Drive and Continental Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 71st Drive and Continental Avenue. 
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Backfilling and restoration of sections on Metropolitan Avenue between 72nd Avenue and 71st Drive.
  • Saw cutting and milling from Continental Avenue to 70th Drive on Friday, October 09, 2026.
  • No construction Saturday October 10,2026through Monday, October 12th,2026. For your safety, please do not enter job work zones during or after construction hours.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Avenue and Continental Avenue. 
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Backfilling of sections on Metropolitan Avenue between 72nd Avenue and 71st Drive.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.
  • No construction on Saturday 09/26/2026 due to inclement weather. Our crews will secure the job site to the best of their ability to brace for the weather.  For your safety, please do not enter job work zones during or after construction hours.
     

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Avenue and Continental Avenue. 
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Backfilling of sections on Metropolitan Avenue near Dante's Pizza.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.
  • No construction on Saturday 09/26/2026 due to inclement weather. Our crews will secure the job site to the best of their ability to brace for the weather.  For your safety, please do not enter job work zones during or after construction hours.
     

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue. 
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.
     

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue. 
  • Continued backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Road.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.
     

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue. 
  • Continued backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.
     


Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue. 
  • Backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and Continental Avenue and at the intersection of Ascan Avenue and Metropolitan Avenue.
  • Backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue. Meters on Metropolitan Avenue are still in effect outside our work zones.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between 72nd Road and 72nd Avenue and at the intersection of Ascan Avenue and Metropolitan Avenue.
  • Backfilling and temporary restoration of portions of Metropolitan Avenue between 74th Avenue and 72nd Avenue.
  • Saw cutting and asphalt preparations between 72nd Road and Continental Avenue from August 3, 2026 through August 11, 2026.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities: 

  • Continued vacuum excavations and installation of infrastructure on Metropolitan Avenue between Ascan Avenue and 72nd Avenue.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue.

Please visit our FAQs tab or construction schedule tab for more information regarding timelines, parking, plate noise, and other common questions/concerns.

The neighborhood can expect the following activities:

  • Continued Vacuum excavations and installation of infrastructure on Metropolitan Avenue between Ascan Avenue and 72nd Avenue. Please see the project map for updates.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.
  • Please note: Parking will be impacted on Metropolitan Avenue.

The neighborhood can expect the following activities:

  • Continued Vacuum excavations on Metropolitan Avenue between Ascan Avenue and 72nd Road.
  • Installation of infrastructure.
  • Prefabrication and welding activities in our yard at 100-32 Metropolitan Avenue.

The neighborhood can expect the following activities:

  • Mobilization on Metropolitan Avenue and Ascan Avenue.
  • Vacuum excavations on Metropolitan Avenue and Ascan Avenue.

For your safety, please do not enter work zones and be mindful of traffic cones and signage. 

work zone

2025

  • Continued inspections and test hole excavations within our property on 70th Drive and Metropolitan Avenue
  • Temporary and then final restoration of the site
  • Crews will be conducting inspections within our property on 70th Drive and Metropolitan Avenue
  • Small excavations for test holes to inspect existing underground utilities